The Virgin Islands Water and Power Authority has announced that Crown Bay Road in downtown St. Thomas will be limited to one lane for two weeks beginning October 10 as crews install underground electrical infrastructure for the Feeder 9A project. The work, performed by contractor Haugland Virgin Islands, includes trenching, conduit placement, concrete pouring, backfilling and surface restoration. WAPA said alternating one‑lane traffic will keep access open for businesses along the corridor.
The authority estimates the project will cost $12.8 million and is financed through the FEMA 406 Hazard Mitigation Grant Program. “The $12.8 million project is funded through the FEMA 406 Hazard Mitigation Grant Program,” WAPA stated.
In a separate notice, WAPA advised motorists to expect temporary delays and to follow posted signs. “WAPA advises the public of temporary traffic impacts along Crown Bay Road,” the agency said.